For Immediate Release: Tuesday, December 10, 2024 4:02 PM
New Orleans, La - The Sewerage and Water Board of New Orleans (SWBNO) contractor, Wallace C Drennan, is scheduled to make water main vault repairs on Decatur Street and Wilkinson Street starting Wednesday, December 11, 2024. The contractor will be executing lane closures to facilitate repairing the water main vault. The lane closures are expected to last up to six days for the needed repairs and paving restoration.
Signage and traffic control measures such as barrels and fencing are onsite to direct drivers and pedestrians.
Work Phase:
We appreciate your patience and understanding as we undertake these important repairs to improve our water system.
For any questions or further assistance, please contact: outreach@swbno.org.
###